Early stages of foundation construction showing 6 inch terrafoam perimeter insulation installed. -
Ready for concrete pour.
Note: 6 inch perimeter foam insulation being utilized as concrete forms. -
Post and beam structure up and ready for roof trusses. -
Corner post and beam details showing everything including bottom bale ladder up to top wall beam. -
Bale work completed in garage. No stucco wire used. Note: diagnal 2x4 bracing used for alignment for bale walls. -
Strawbale work just finished under galvanized garage roof. -
Final bale being cut for installation.
Note: Vertical brace used for corner bale alignment. -
This framing view highlights a door frame fastened to the bottom bale ladder. -
Corner bracing removed after first coat of stucco. -
Corner bracing will be removed after first coat. See close up of next photo. -
Close up showing penetration into non-wired straw bale wall showing excellent penetration.